Major Projects | Works executed
Splitter II Project in Luján de Cuyo Refinery
Client
RepsolYPF
Location
Luján de Cuyo Refinery • Luján de Cuyo • Mendoza • Argentina
Description
Turnkey provision of a Splitter II naphtha fractionation unit, TK-B1 light naphtha storage tank, plus secondary services and supplementary facilities. Including: analysis of basic engineering, detail engineering, provision of equipment and materials, construction, assembly, precommissioning, commissioning and start-up assistance.
Processing data
Splitter II design capacity is 60 m3/h; it is the initial phase of a process aimed to reduce sulfur content in a stream of heavy cracked naphtha - HCN, to 50 ppm sulfur content in total weight.
Period of execution
Subscription of Agreement: July 2005.
Plant ready for Splitter II and TK-B1 start up:
November 2006.
Provisional Acceptance
December 2006.