Completed Works

Work
List
Next
Prev
Gathering Networks, Primary Separation and Dewatering Batteries, Gas Treatment Plant and Connecting Pipes
CUSTOMER: U.T.E. SANTA CRUZ II
PLACE: An Aike and Barda Oilfields • Santa Cruz • Argentina
DESCRIPTION

Turnkey project including: 2 TEG gas primary separation and dewatering batteries in An Aike (1.5 Mm3/day); one primary separation unit (1.0 Mm3/day), one water and hydrocarbons dew point plant for a gas flow of 3.1 Mm3/day, and a treatment and re-injection unit for formation water in Barda Las Vegas; gas gathering networks, connecting pipes and electric power generation system (2 x 900 kVA)

Year

2000

Bookmark and Share